Decision details

Guildhall Project, Bury St Edmunds

Decision Maker: St Edmundsbury Cabinet

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Purpose:

The Cabinet will receive an update on this existing project (being led by the Bury St Edmunds Heritage Trust) at its May 2016 or a subsequent meeting.

Decision:

RESOLVED:

That:

 

(1)     the content of Report No: CAB/SE/16/028 be noted;

 

(2)     the Director be authorised to update the 2013 Memorandum of Understanding for the Guildhall Project on the basis outlined in paragraphs 1.5 and 1.8 of Report No: CAB/SE/16/028.

 

RECOMMENDED TO COUNCIL (28 June 2016):

 

(3)     The principle of making a bridging loan in autumn 2016 to enable progression of the conservation works at the Guildhall, be approved; and

 

(4)     if the loan is required, the Head of Resources and Performance, in consultation with the Leader, the Portfolio Holder for Resources and Performance and the Services Manager (Legal), be authorised to negotiate and agree the terms of such a loan with the Bury St Edmunds Heritage Trust Ltd and/or the Guildhall Feoffment Trust and to issue the funding and necessary legal agreements, taking into consideration the Council’s loans policy and subject to the value of the loan not exceeding a professional valuation of 79 Whiting Street, Bury St Edmunds (against which it will be secured).

Report author: Alex Wilson

Publication date: 16/06/2016

Date of decision: 14/06/2016

Decided at meeting: 14/06/2016 - St Edmundsbury Cabinet

Effective from: 24/06/2016

Accompanying Documents: