Agenda item - Planning Application DC/17/1252/FUL - Land off Cavendish Road, Clare (Report No: DEV/WS/21/038)

Agenda item

Planning Application DC/17/1252/FUL - Land off Cavendish Road, Clare (Report No: DEV/WS/21/038)

Report No: DEV/WS/21/038

 

Planning Application - 53no. dwellings with associated access, infrastructure and landscaping

Minutes:

(Councillor Nick Clarke advised the meeting, in the interests of transparency, that he had originally registered to speak as Ward Member on the application. Subsequently he was then asked to act as substitute at the meeting by Councillor Peter Stevens. Accordingly, Councillor Clarke withdrew his registration to speak as Ward Member, which was now being undertaken by Councillor Marion Rushbook.)

 

Planning Application - 53no. dwellings with associated access, infrastructure and landscaping

 

Members were advised that this application was originally submitted in 2017 but its determination was delayed due to landownership issues which were now resolved.

 

The Committee were informed that the proposal had been reassessed against current policy and a fresh and full consultation had been carried out.

 

The site had also previously been the subject of consultation with key stakeholders and the local community as part of the preparation and adoption of a Development Brief, which was formally adopted by the Council in 2016.

 

The application was referred to the Development Control Committee following a call-in from Ward Member Councillor Nick Clarke (Clare, Hundon and Kedington).

 

Clare Town Council had also raised concerns with the proposal which was in conflict with the Officer’s recommendation of approval, subject to the completion of a S106 agreement and conditions as set out in Paragraph 9.0 of Report No DEV/WS/21/038.

 

The Principal Planning Officer drew attention to the following conditions which required amendment:

·         Condition 2 – the most up to date drawing numbers for the elevations and floor plans were included in the supplementary ‘late papers’ issued after publication of the agenda;

·         Condition 9 – a second drawing number was to be inserted (as it only referenced one); and

·         Conditions 26 and 28 – were to be reworded to reflect that development, and therefore occupation, would take place in phases.

 

As part of her presentation the Officer showed videos of the site by way of a virtual ‘site visit’.

 

Speakers:    Margaret Goodwin (Clare Society) spoke against the application

                   Councillor Paul Bishop (Chair, Clare Town Council) spoke against the application

                   Councillor Marion Rushbrook (Ward Member: Clare, Hundon and Kedington) spoke against the application

                   Henrik Darlington (developer) spoke in support of the application

 

Councillor Nick Clarke spoke on the application and stressed the importance of encouraging foot and cycle access from the site into central Clare; which required further thought in view of the narrow and partially blocked (with telegraph poles) pavement.

 

Councillor Clarke also echoed the concerns raised by the Town Council in respect of the impact on the highways network and highlighted the need for some form of mitigation.

 

Councillor John Burns also highlighted highways concerns and referenced photographs that Clare Town Council/the Clare Society had emailed Committee Members with. He asked if a condition could be added to the recommendation in respect of amending the relevant Traffic Regulation Order to extend the 30mph speed limit eastwards.

 

The Principal Planning Officer explained that it would not be possible to add a condition in this regard because Suffolk County Council, acting as the statutory consultee for the Highways Authority, had not deemed it necessary.

 

Councillor Susan Glossop raised disappointment that a representative from the Highways Authority was not in attendance. Councillor John Burns similarly asked that discussion be facilitated between the Highways Authority, West Suffolk Council and Clare Town Council in respect of the application in question.

 

Some Members raised issue with the layout of the scheme; with particular reservations being voiced at the alleyways behind the dwellings leading to/from parking areas. The Case Officer explained that the development had been designed in that way in order to prevent parking from dominating the frontage.

 

In response to other comments made during the debate the Principal Planning Officer advised:

Growth – the Committee were reminded that housing allocation within the Local Plan was not a ‘cap’ on development and that windfall sites could always come forward;

Affordable Housing – current policies did not permit rounding upwards when the percentage of properties was calculated per development. Whilst policies did exist that prevented clusters of affordable housing over a certain number, there was a balance to be struck as housing providers favoured the properties being within smaller clusters in developments; and

Renewables – it would not be possible to add additional conditions in respect of sustainable heating, solar panels, broadband etc as current policies did not require these.

 

Councillor Ian Houlder proposed that the application be approved as per the Officer recommendation. This was duly seconded by Councillor David Roach.

 

Upon being put to the vote and with 12 voting for the motion and 4 against it was resolved that

 

Decision

 

Planning permission be GRANTED subject to:

 

1.)The completion of a S106 agreement to secure the following (subject to meeting the CIL Reg 122 tests):

·         Policy compliant level and tenure split of affordable housing

·         Contribution in respect of the 0.9 part affordable dwelling.

·         Education contribution – Secondary School £213,975.00 and sixth £47,550.00

·         Libraries contribution (if deemed compliant with CIL Regulation 122)

·         Waste contribution (if deemed compliant with CIL Regulation 122)

·         Public rights of way improvements - £74,500

·         Off site Play and Recreation - £39,822.00

·         NHS - £31,800.00

In the event that there are any substantive changes to the S106 package, then this will go back to the Chair of the Development Control Committee to determine whether it is necessary to bring the proposals back before the Committee.

 

And

 

2.)The following conditions:

 

1.   Time The development hereby permitted shall be begun not later than 3 years from the date of this permission.

2.   Approved Plans The development hereby permitted shall not be carried out except in complete accordance with the details shown on the approved plans and documents.

3.   Construction and site management plan – pre commencement Prior to the development commencing a comprehensive Construction and Site Management Programme shall be submitted to the Local Planning Authority for approval. The approved programme shall be implemented throughout the development phase, unless the Local Planning Authority gives written consent to any variation.

The programme shall include:-

a.            site set-up and general arrangements for storing plant, including cranes, materials, machinery and equipment, offices and other facilities;

b.            access arrangements for contractors’ vehicles (locations and times), parking and turning for vehicles of site personnel, operatives and visitors, loading and unloading of plant and materials and a methodology for avoiding mud from the site tracking onto the highway with a strategy for remedy of this should it occur.

c.            noise method statements and noise levels for each construction activity including any piling and excavation operations;

d.            dust, dirt and vibration method statements and arrangements;

e.            site lighting.

4.   Construction Surface Water - pre-commencement No development shall commence until details of a Construction Surface Water Management Plan (CSWMP) detailing how surface water and storm water will be managed on the site during construction (including demolition and site clearance operations) is submitted to and agreed in writing by the local planning authority. The CSWMP shall be implemented and thereafter managed and maintained in accordance with the approved plan for the duration of construction. The approved CSWMP and shall include: method statements, scaled and dimensioned plans and drawings detailing surface water management proposals to include :-

1.       Temporary drainage systems

2.       Measures for managing pollution / water quality and protecting controlled waters and watercourses

3.       Measures for managing any on or offsite flood risk associated with construction

5.   Detailed surface water drainage – pre-commencement No development shall commence until a detailed surface water drainage scheme for the site, based on the agreed Flood Risk Assessment and Drainage Strategy (FRADS) by GH Bullard Associates, ref. 045/2011/FRA Rev E and dated Feb 2018 has been submitted to and approved in writing by the local planning authority. The scheme shall subsequently be implemented in accordance with the approved details before the development is completed. The scheme shall include a restriction in run-off to greenfield runoff rates (5l/s) and at least 734m3 of surface water storage on site, as outlined in the FRADS. Details to be submitted include:-

1.       Dimensioned drawings showing all aspects of the surface water drainage system (including an impermeable area plan). Section details of the proposed storage areas shall also be submitted showing the level benches.

2.       Modelling or similar method shall be submitted to demonstrate that the surface water discharge to the receiving watercourse will be restricted to 5l/s for all events up to the critical 1 in 100yr +CC rainfall event.

3.       Modelling of the surface water drainage scheme to show that the attenuation/infiltration features will contain the 1 in 100yr rainfall event including climate change.

4.       Modelling of the pipe network in the 1 in 30yr rainfall event to show no above ground flooding.

5.       Modelling of the volumes of any above ground flooding from the pipe network in a 100yr + climate change rainfall event, along with topographic plans showing where water will flow and be stored to ensure there is no flooding to buildings on the site and there is no flooding in the immediate area due to offsite flows. These flow paths will demonstrate that the risks to people are kept to a minimum.

6.       Demonstration of adequate treatment stages for water quality control shall be submitted - SuDS features should demonstrate betterment to water quality, especially if discharging towards a watercourse.

7.       A management and maintenance plan for the lifetime of the development which shall include the arrangements for adoption by any public body or statutory undertaker, or any other arrangements to secure the operation of the sustainable drainage system throughout its lifetime.

8.       Arrangements to enable any surface water drainage within any private properties to be accessible and maintained including information and advice on responsibilities to be supplied to future owners.

6.   Site Access - Pre commencement Before any plant, machinery or materials are brought onto the site and prior to the first commencement of development, full details of the proposed construction site access (including the position of any gates to be erected, visibility splays provided and drainage or other existing infrastructure to be altered) shall be submitted to and approved in writing by the Local Planning Authority. The approved access shall be laid out and constructed in its entirety prior to first use or any other part of the development taking place and no other access to the site shall be used during the construction phase.        

7.   Deliveries Management Plan - pre commencement All HGV and construction traffic movements to and from the site over the duration of the construction period shall be subject to a Deliveries Management Plan which shall be submitted to the planning authority for approval a minimum of 28 days before any deliveries of materials commence.

No HGV movements shall be permitted to and from the site other than in accordance with the routes defined in the Plan.

The site operator shall maintain a register of complaints and record of actions taken to deal with such complaints at the site office as specified in the Plan throughout the period of occupation of the site. 

8.   Access details - Prior to access construction Prior to the access being constructed details of the access and associated works, (including layout, levels, gradients, surfacing and means of surface water drainage), shall be submitted to and approved in writing by the Local Planning Authority.

The ditch beneath the proposed access shall be piped or bridged in accordance with details which previously shall have been submitted to and approved in writing by the Local Planning Authority and shall be retained thereafter in its approved form.        

9.   Offsite highway work - pre commencement No part of the development shall be commenced until details of the proposed off-site highway improvements indicatively shown on Drawing Nos. 045/2011/22 REV P5 and 045/2011/21rev P2 have been submitted to and approved in writing by the Local Planning Authority. The approved scheme shall be laid out and constructed in its entirety prior to occupation.

10.                Internal road details - pre commencement Before the development is commenced, details of the estate roads and footpaths, (including layout, levels, street lights, gradients, surfacing and means of surface water drainage), shall be submitted to and approved in writing by the Local Planning Authority.

11.Fire Hydrants – pre-commencement No development shall commence until a scheme for the provision of fire hydrants within the application site have been submitted to and approved in writing by the Local Planning Authority. No part of the development shall be occupied or brought into use until the fire hydrants have been provided in accordance with the approved scheme. Thereafter the hydrants shall be retained in their approved form unless the prior written consent of the Local Planning Authority is obtained for any variation.    

12.   Tree protection - pre commencement The trees shown on drawing number LSDP11418.01 Rev A shall be protected in accordance with BS5837: 2012  before any equipment, machinery or materials are brought onto the site for the purposes of development and shall continue to be so protected during the period of construction and until all equipment, machinery and surplus materials have been removed from the site. Within the fenced area no work shall take place; no materials shall be stored; no oil or other chemicals shall be stored or disposed of; no concrete, mortar or plaster shall be mixed; no fires shall be started; no service trenches shall be dug; no soil shall be removed or ground level changed at any time, without the prior written consent of the Local Planning Authority.

13.   Construction hours - during construction The hours of construction activities, including deliveries to the site and the removal of excavated materials and waste from the site, shall be limited to between 07:00 and 18:00 hours on Mondays to Fridays and 08:00 and 15:00 hours on Saturdays. No construction activities shall take place at the application site on Sundays, Bank or Public Holidays.

14.Vegetation Clearance – during construction Notwithstanding the approved details or any details submitted in compliance with the requirements of any other conditions imposed upon this grant of planning permission, there shall be no clearance of any existing vegetation upon the site or other site clearance works during the bird nesting season (March - September inclusive), without the written agreement of the local planning authority following the submission of survey information, undertaken by a competent ecologist to assess the nesting bird activity on site during this period.    

15.   Sustainable Design and Construction details – pre-above ground No development above ground level shall take place until, an energy and sustainability statement for the development has been submitted to and approved in writing by the Local Planning Authority. The statement shall outline how the development adheres to broad principles of sustainable design and construction and how energy efficiency will be optimised through the use of renewable and other technology, materials, insulation and construction techniques. The development shall be carried out in accordance with the approved strategy.

16.Designing out opportunities for crime – pre-above ground

No above ground construction shall take place until the details of the measures and strategies to design out opportunities for crime have been submitted to and approved in writing by the Local Planning Authority. The measures shall include as a minimum:

·      details of the anti-crime features to be provided for each dwelling     including the use of security lighting, where appropriate;

·      details of measures to improve the safety of rear access paths including the use of gates, boundary treatments and lighting; and

·      Details of boundary treatments to provide safe and secure private amenity spaces and clear demarcation of public and private spaces.

All work shall be carried out in accordance with the approved details.

17.   Waste Strategy – pre-above ground Notwithstanding the information submitted with the application, no development above ground level shall take place until a waste strategy has been submitted to the local planning authority and agreed in writing.

Such a strategy shall include full details of the bin storage and collection points including presentation areas for individual dwellings and groups of dwellings. The details shall clearly indicate presentation points and the properties they would serve and shall include details of the distances from dwellings to those bin presentation points where they are not on the property.

18.   Fire hydrants – pre above ground No above ground construction shall take place until a scheme for the provision of fire hydrants has been submitted to the local planning authority and agreed in writing. The fire hydrants shall be provided in accordance with the approved scheme and thereafter retained in their approved from.

19.   Boundary Treatment - pre above ground Notwithstanding the details previously submitted in relation to the boundaries of the site, no construction above ground level shall take place on the site until full details of the boundary treatments within the site have been submitted to and approved in writing by the Local Planning Authority. The details shall specify the siting, design, height and materials of the screen walls/fences to be constructed or erected and/or the species, spacing and height of hedging to be retained and / or planted and in the case of hard boundaries must include provision for hedgehog permeability (with gaps of 13x13cm at ground level).

         The approved boundary treatments in relation to residential plots shall be constructed or erected before the dwelling to which it relates is first occupied. Other on site boundary treatments shall be completed before the first occupation of any dwelling on the site. Where boundaries include soft landscaping, planting shall be done so within 12 months of the date on which those details are agreed or in accordance with a timetable agreed in writing with the local planning authority.  Any planting removed, dying, being severely damaged or becoming seriously diseased within five years of planting shall be replaced by soft landscaping of similar size and species to those originally required to be planted.

20.Hard landscaping - pre above ground No construction above ground level shall take place until full details of the hard landscaping for the site has been submitted to and approved in writing by the Local Planning Authority. These details shall include proposed finished levels and contours showing earthworks and mounding; surfacing materials; means of enclosure; car parking layouts; other vehicle and pedestrian access and circulations areas; hard surfacing materials; minor artefacts and structures (for example furniture, refuse and/or other storage units, signs, lighting and similar features); proposed and existing functional services above and below ground (for example drainage, power, communications cables and pipelines, indicating lines, manholes, supports and other technical features. The scheme shall be implemented prior to the first occupation of any part of the development (or within such extended period as may first be agreed in writing with the Local Planning Authority).

21.      Soft Landscaping and Biodiversity Enhancement Details - Pre above ground Notwithstanding the structural landscaping details provided, no above ground construction shall take place until there has been submitted to and approved in writing by the Local Planning Authority a scheme of soft landscaping for the site drawn to a scale of not less than 1:200. The soft landscaping details shall include planting plans; written specifications (including cultivation and other operations associated with plant and grass establishment); schedules of plants noting species, plant sizes and proposed numbers/ densities.  Planting should include native species and a mixture of trees and shrubs that provide nectar, fruit, or seeds to maximise foraging opportunities for invertebrates, birds, and bats.

Additional biodiversity enhancements should include the creation of additional hibernation features suitable for use by amphibians and the provision of artificial bird and/or bat boxes targeted towards species that are notable regionally or nationally.

The approved scheme of soft landscaping and biodiversity enhancement works shall be implemented not later than the first planting season following commencement of the development (or within such extended period as may first be agreed in writing with the Local Planning Authority). Any planting removed, dying or becoming seriously damaged or diseased within five years of planting shall be replaced within the first available planting season thereafter with planting of similar size and species unless the Local Planning Authority gives written consent for any variation.

22.   Materials - prior to construction

No construction using visible facing or roofing materials take place until details of those facing and roofing materials to be used have been submitted to and approved in writing by the Local Planning Authority. The development shall be carried out in accordance with the approved details.      

23.   Access Surface Water - pre above ground Prior to any construction above ground level taking place on the site, details shall be submitted to and approved in writing by the Local Planning Authority showing the means to prevent the discharge of surface water from the development onto the highway. The approved scheme shall be carried out in its entirety before the access is first used and shall be retained thereafter in its approved form.

24.   Visibility splays - prior to first use of the access Before the access is first used visibility splays shall be provided as shown on Drawing No. 045/2011/22 REV P5 with an X dimension of 2.4 metres and thereafter retained in the specified form. Notwithstanding the provisions of Part 2 Class A of the Town & Country Planning (General Permitted Development) Order 1995 (or any Order revoking and re-enacting that Order with or without modification) no obstruction over 0.6 metres high shall be erected, constructed, planted or permitted to grow within the areas of the visibility splays

25.         Carriageway and footway construction - prior to first occupation No dwelling shall be occupied until the carriageways and footways serving that dwelling have been constructed to at least Binder course level or better in accordance with the approved details.

26.                Parking - prior to first occupation of relevant dwellings Prior to the first occupation of any dwelling within the development hereby approved, the areas shown on Drawing No. 4164-01 REV K for the purposes of manoeuvring and parking of vehicles and for the purposes of secure cycle storage for that dwelling, must have been provided and be available for use.  Thereafter, those areas shall be retained and used for no other purposes.

27.                Cycle storage for dwellings – Prior to occupation Prior to the first occupation of any dwelling, the cycle storage for that dwelling, as indicated on drawing no. 8946/22 rev C shall be provided. Where it is indicated that this will be within the rear garden it shall be provided in the form of enclosed, secure storage with a minimum size of 3m² shall be provided prior to the first occupation of that dwelling.

28.                Refuse/recycling bins - prior to first occupation of relevant dwellings Prior to the first occupation of any dwelling within the development hereby approved, the areas to be provided for storage and presentation for collection of Refuse/Recycling bins as shown on Drawing No. 4164-01 REV K to serve that dwelling must have been provided and be available for use.  Thereafter, those areas shall be retained and used for no other purposes.

29.Public Open Space and landscape management and maintenance – prior to first occupation Prior to the first occupation, full details of the proposed arrangements for future management and maintenance of the public open space, including the associated suds features, shall be submitted to the local planning authority and agreed in writing.

The details must include a full landscape management plan, including long term design objectives, and maintenance schedules for all soft landscape areas, included associated suds features (other than small privately owned domestic gardens) together with a timetable for the implementation.

The details must also specify the appointed management company or adopting body, and the proposed management arrangement. The open spaces shall thereafter managed and maintained in accordance with agreed details.

30.EV charging – prior to first occupation Prior to first occupation of any dwelling with off street, on plot, parking (Plots 15-16, 19-34, 38, 46 to 53), the relevant dwelling shall be provided with a suitable consumer unit and wiring to allow the future installation of an electric vehicle charge point capable of 7kWh charging at a reasonably and practicably accessible location.

          Prior to first occupation of dwellings served by a parking court, the relevant parking court shall be provided with two electric vehicle charge points capable of at least a 7kWh charge, available for communal use.

31.   Suds Components details - prior to first occupation No dwelling hereby permitted shall not be occupied until details of all Sustainable Urban Drainage System components and piped networks have been submitted, in an approved form, to and approved in writing by the Local Planning Authority for inclusion on the Lead Local Flood Authority's Flood Risk Asset Register.

32.   Water consumption - prior to occupation No individual dwelling hereby   approved shall be occupied until the optional requirement for water consumption (110 litres use per person per day) in Part G of the Building Regulations has been complied with for that dwelling.