Issue - decisions

West Suffolk Operational Hub

14/12/2017 - West Suffolk Operational Hub

RECOMMENDED TO COUNCIL: (20 December 2017)

 

That:-

1.           Report No: CAB/FH/17/057 and its Appendices, be noted.

 

2.           The allocation of an additional £589,000 to the Council’s Capital Programme, funded in line with paragraphs 5.14 - 5.17 of Report No: CAB/FH/17/057, be approved.

 

3.           Subject to receiving a planning consent:-

a)           the Council’s option to procure land at Hollow Road Farm be exercised;

b)           With Suffolk County Council and St Edmundsbury Borough Council, a contract be entered into for the construction of the West Suffolk Operational Hub at Hollow Road Farm; and

 

4.           It be agreed for the Council’s Section 151 Officer to make the necessary changes to the Council’s 2017/18 prudential indicators as a result of recommendation 2. above.