Issue - decisions

Sunnica Energy Farm Nationally Significant Infrastructure Project (NSIP): Statement of Common Ground

08/02/2023 - Sunnica Energy Farm Nationally Significant Infrastructure Project (NSIP): Statement of Common Ground

Resolved:

 

That

1.       The draft Statement of Common Ground (SoCG) be approved (A draft of which is included at Appendix 1 to Report number CAB/WS/23/012).

 

2.       The Director (Planning and Growth), in consultation with the Portfolio Holder for Planning, be authorised to make amendments to the draft Statement of Common Ground, prior to its submission into the Examination by the required deadline of 13 March 2023.